The T on the rail tracks coming out of a tunnel, approaching the Mt. Lebanon stop.

Roads & Transportation

Road Construction

In Mt. Lebanon, we have two types of road construction: Utility-related road repair, which happens when the gas, electric or water company dig into a street to make a repair. Most unplanned road repairs are this type. The municipality does not have control over when and where this type of repair happens. Sometimes, we are not even notified. If we are notified, we will place it on this page, under utility-related road repair.

We also have road surfacing and construction, which is part of the yearly municipal road improvement contract. We will always contact affected residents about this type of repair. We also will post it here every construction season so all drivers can become aware of it.

Pennsylvania American Water Company Work

Seminole Drive

Contractors for the water company will replace existing water mains on Seminole Drive from Allendale Place to Iroquois Drive.

Work will be Wednesday, November 19 through December 5, weather permitting. Work hours will be 7 a.m. to 5 p.m. Monday through Friday. Expect temporary road restrictions and traffic delays in the work area.

Lakemont and Kurt Drive

Contractors for the water company will be replacing existing water mains and related infrastructure. Work continues, weather permitting, Monday through Friday, from 7 a.m. to 5 p.m. Final street restoration will be in Spring 2026.

Lakemont will be closed between Larchdale and Kurt Monday through Friday from 7 a.m. to 3 p.m. during work.

Expect additional temporary road restrictions and traffic delays in the work area. Short-term water service interruptions will be necessary at times. Impacted residents will receive notice from the contractor whenever possible. Construction equipment and materials will be staged along the project area.

Vermont Ave./Roycroft Ave. (from 100 Roycroft Ave. to 145 Hoodridge Drive)

Roycroft Ave and Vermont Ave will be paved starting Monday, November 24 and lasting through December 5. They will be on holiday break Thanksgiving through that Monday.

Lindenwood Avenue

Lindenwood Avenue and Richland Road. Work continues through November 21.

Crews will work on weekdays between 7 a.m. and 5 p.m. Temporary traffic restrictions will be in place during
construction. The company expects to complete the main installation, including connecting all customer
service lines to the new mains, along with final restoration and paving, later in the schedule.

During construction, customers might experience temporary service interruptions, discolored water,
and/or lower-than-normal water pressure. Crews will work as quickly as possible to shorten the length of
these temporary inconveniences. For more information, contact Pennsylvania American Water’s customer
service center at 1-800-565-7292.


Peoples Gas projects

Newburn – 600 to Morrison; Morrison – Newburn to 169 Morrison

Newburn Drive gas main installation. Work is still ongoing.

Shady Drive West

Line will be replaced from Coolidge to Mapleton, odd side. Work will be October 20 through November 7.

Peoples Gas info and phone: Call: 1.800.764.0111, Mon. – Fri. 7 a.m. – 5 p.m. EST


Columbia Gas projects

We post here as soon as we have information, even if it is in planning stages. All completion dates are estimated and do NOT include road restoration, which Mt. Lebanon requires and will be completed later.

Sage

Gas line replacement for 451 to 509 Sage. Work continues.

Arden Road, Overlook Drive, North Meadowcroft Avenue, Beverly Road, Parker Drive, McFarland Road, Layton Avenue and Anapolis Avenue

Active — estimated duration, three months from late August

Jayson Avenue gas line replacement

Jayson – 975 LF Rae to Mapleton 

Project is ongoing.

Columbia Gas info and phone: Call 1-888-460-4332 Monday – Friday, 7 a.m. – 7 p.m. ET.


Projects near us that may affect you

None at the moment but check back.


Reconstruction

The 2025 Road Reconstruction program is complete!

Learn how streets are selected for our municipal road improvement program on our Road Work 101 page.

The 2025 summer reconstruction program as approved by the Commission:

Craig CourtAnawanda Avenue to Cul De Sac
Crystal DriveGypsy Lane to Castle Shannon Boulevard
Helen DriveTheodan to Dollar General Driveway
Old Hickory RoadPin Oak Road to 904 Old Hickory Road
Ordale Boulevard1480 Washington Road to Cherokee Island
Eisenhower Drive 829 Eisenhower to Ridgeview Drive
Pinoak RoadSweet Gum to Moffett

View an Interactive Road Project Map  to view streets that were reconstructed in 2025 View the reconstruction schedule (updated regularly.)


Steps 1-2 from the linked Road Work page will be completed on all streets prior to Steps 3-6 being completed. Therefore there will be some time after work has started on your street when no one will be working, because they are completing work on the other streets.

The program is generally scheduled to begin in May and rebuilding your street will create some temporary inconvenience. We appreciate your patience as we work to complete a major project that will enhance our community and help ensure your street lasts for another 30 years. Unlike periodic patching and resurfacing, street reconstruction involves removing the old base, replacing deteriorated curb and installing new subsurface drainage before applying a new surface.

During the phases of reconstruction, you will not be able to park on your street. When you cannot use your street or driveway, you may park during the day and overnight on nearby streets where it is legal. You do not have to contact the police department. The municipality will notify the police department for you. Please be conscious of other residents when you are parking on the streets. Do not block driveways and be aware of residents’ need to have ample room to back out of their driveways when parking on the streets. The contractor will leave a notice at your front door a few days before construction begins.

Emergency fire, police and medical rescue service will continue as usual, and regular garbage pickup and mail delivery will be maintained. If your street is closed and you need to pick up or drop off a person with a disability or a medical condition, please talk with the Contractor’s foreman. If necessary, he can arrange to have that person transported out of the construction area.

If you are planning to move or are expecting a large delivery during the process, please notify the municipal engineer at (412) 409-2398 as soon as possible. Arrangements will be made if possible; however, you may need to modify your schedule. If you have an irrigation system or an invisible dog fence please let the Contractor’s foreman know prior to the start of construction. These systems are not marked on the surface so there is the potential for accidental removal by the contractor.


Resurfacing

The 2025 summer resurfacing program is complete. Here are the streets approved by the Commission:

Beverly RoadMarlin Drive East to Marlin Drive West
Catalpa PlaceParkside Avenue to Richland Road
Cedar BoulevardMorgan Drive to Hollycrest Drive
Lindendale DriveKurt Drive to 1022 Lindendale Drive
North Meadowcroft AvenueKenforest Drive to Twin Hills Drive
Oxford BoulevardWorchester Drive to Pembroke Drive
Sleepy Hollow RoadRichland Road to Valley Park Drive
Woodland DriveWainwright Drive to Vermont Avenue
Brafferton Dr & Old Farm RdSleepy Hollow to Highvue
Cedar BoulevardLindendale to 1183 Cedar
St. Clair DriveEntire Road

View an Interactive Road Project Map  to view streets resurfaced in 2025. View the resurfacing schedule (updated regularly) to see when projects were completed.

Construction schedules may need to be revised during the project due to unforeseen issues, such as utility service conflicts. Also the schedule may be affected by poor weather conditions.


Roads rejuvenated in 2025 (final number is square feet done)

Atlanta Place, Baywood to Summit Alley 1265
Cedar, Cochran Road to Summitt Alley 2375
MacArthur, Wainwright to 878 MacArthur 2100
North Meadowcroft, Greenlawn to Twin Hills 2590
Oak Park Place, Old Hickory to Old Hickory 4450
Woodland, Ridgeview to 102 Woodland 1815
Birch Avenue, Sunset Dr to Scott Road 970
Fernwood Ave, Parkside Ave to Dead End 1335
Firwood Drive, Larchdale Dr to 1145 Firwood 2315
Mapleton Ave, Bower Hill Rd to Rae Avenue 2140
Meridian Dr, Haverhill Road to Country Club Dr 1925
Oregon Trail, Connor Road Municipal Line – New Pavement 1040
Rawley Drive, Firwood Drive to Lakemont Drive 1040
Cedar Blvd / Salem Cedar Blvd to Salem Dr Intersection/New Pavement 1500
Helen Drive, Banksville Rd to Dollar General Driveway 515
Florida Ave, (ALT) Cedar Blvd to 666 Florida 495
Illinois Ave, (ALT) Mississippi to End 945
Mississippi Ave, New Pavement to Municipal Line – End 2345


Brick Streets

Mt. Lebanon’s Historic Brick Streets are cherished parts of our neighborhood character. As such, the Mt. Lebanon Commission passed a brick streets policy in 2023 to help ensure the continuity of key brick roads. Read the policy here.

Each year, the municipality budgets money to repair sections of our brick streets. Because the work is variable, the list is not final until the project is complete each year, based on the amount of damage and time and materials needed to do the repairs within budget.