Swim Center Renovation

Hooray! Swim Center is now open!


 The renovation includes:

Pool

  • Replace plumbing and gutters.
  • Replace filtration system.
  • Add pool heater.
  • Sand blast and epoxy paint pool.
  • Replace concrete deck/modify design.
  • Replace deck equipment.
  • Add zero depth beach entry.
  • Perform renovations to meet ADA codes.
  • Add dual slide tower.
  • Add poolside climbing wall.

Bathhouse

  • Perform renovations to meet ADA codes and add family changing facilities.
  • Perform interior cosmetic and amenity upgrades.
  • Renovate, redesign, and upgrade all HVAC, plumbing and electrical systems.
  • Improve the efficiency of the patron admission process, and allow direct entry to the facility without passing through the changing areas.
Groundbreaking Ceremony
On Friday, November 15, commissioners, staff, local elected officials and media gathered to watch the groundbreaking for the pool renovation project.

Lebo_pool_groundbreaking2_GeorgeMendel.jpg
Photo credit: George Mendel.
Photo id: Left to right: Commissioner Matt Kluck, Commissioner David Brumfield, Commissioner Kelly Fraasch, Commissioner John Bendel, Recreation Facilities Manager Bob Hlebinsky, Engineer Dan Deiseroth, Architect Mark Edelmann, Municipal Manager Steve Feller, Recreation Director David Donnellan.


Project Updates

6/12/14 Update

  • Snack bar area deck pour 90% complete.
  • Installed shade umbrella tops.
  • Poured long concrete seat wall at zero beach.
  • Completed touch up of all sod.
  • Caulking of pool deck 75% complete.
  • Commenced installation of swimming pool chemical feed system.
  • Completed installation of in-gutter depth markers.
  • Filled the swimming pool.
  • Commenced grouting of tile depth markers and striping on pool deck.
  • Commenced cleanup of the site.

6/05/14 Update
  • Completed installation of aluminum ornamental fencing.
  • Completed installation of glass curtain wall on bathhouse.
  • Completed pool deck on north side of the main pool in front of the bathhouse.
  • Poured deck at zero beach, and sidewalk to diving well.
  • Set shade umbrella posts on footers.
  • Formed one concrete seat wall at zero beach.
  • Set pool heater.
  • Installed sod on east side of facility.
  • Completed setting exterior light poles.
  • Completed sound and data systems.
  • Continued installation of swimming pool plumbing in filter room.
  • Completed installation of gutter covers.
  • Completed painting of the pool tank including racing lanes, targets and depth markers.
  • Completed installation of accessible ramp in leisure pool.
  • Completed diving board installation.
  • Commenced installation of tile depth markers and striping on pool deck.
  • Completed installation of leisure features.

5/30/14 Update
  • Completed painting interior doors and frames.
  • Completed hanging interior doors.
  • Continued installation of windows and counters in admissions booth.
  • Continued installation of aluminum ornamental fencing.
  • Completed installation of bathroom partitions.
  • Continued installation of glass curtain wall on bathhouse.
  • Commenced pouring pool deck on north side of the main pool in front of the bathhouse.
  • Set pool heater enclosure on footers.
  • Installed sod on west end of facility.
  • Continued installation of swimming pool plumbing in filter room.
  • Commenced installation of gutter covers.
  • Painted base coat in pool tank.
  • Commenced painting of racing lanes, targets and depth markers.
  • Commenced installation of accessible ramp in leisure pool.
  • Installed tile apron in zero depth entry.
  • Commenced installation of leisure features.
  • Installed starting blocks.
  • Installed fencing below slide tower.

5/22/14 Update

  • Continued painting interior doors and frames.
  • Commenced hanging interior doors.
  • Completed installation of entrance gates in breezeway.
  • Installed drinking fountains in breezeway.
  • Commenced installation of windows and counters in admissions booth.
  • Continued installation of aluminum ornamental fencing.
  • Continued installation of bathroom partitions.
  • Commenced installation of glass curtain wall on bathhouse.
  • Poured pool deck on south side of diving well, and along east side of pool.
  • Demolished concrete deck along north end of pool.
  • Installed sod on south end of facility.
  • Commenced installation of swimming pool plumbing in filter room.
  • Completed installation of epoxy floor in snack bar.
  • Completed installation of roof coping.
  • Completed installation of bathroom fixtures.
  • Completed installation of decorative lighting on building exterior.
  • Completed installation of interior light fixtures.
  • Completed installation of in-gutter return lines and inlets.
  • Commenced preparation work for pool tank painting.

5/15/14 Update
  • Ceramic tile work in changing rooms complete.
  • Commenced painting interior doors and frames.
  • Commenced installation of entrance gates on breezeway, and aluminum ornamental fencing.
  • Commenced installation of bathroom partitions.
  • Poured pool deck on east side of diving well.
  • Poured zero depth leisure pool floor.
  • Completed installation of the dual slide tower.
  • Formed and poured swimming pool filter tank.
  • Continued painting interior doors and frames.
  • Commenced installation of epoxy floor in snack bar.
  • Commenced installation of roof coping.
  • Commenced installation of bathroom fixtures.
  • Gas line tap and meter set installation complete.
  • Installation of radiant heat panels complete.
  • Installation of exterior light poles on foundations 75% complete.
  • Decorative lighting on building exterior 75% complete.
  • Commenced installation of in-gutter return lines and inlets.
  • Completed installation of zero depth leisure feature plumbing.

5/8/14 Update
  • Completed drywall ceiling installation.
  • Ceramic tile work in changing rooms 90% complete.
  • Commenced painting of interior ceilings.
  • Set cabinets and countertops in snack bar.
  • Poured pool deck on west side of pool.
  • Poured footers for dual slide tower.
  • Poured floor for swimming pool filter tank.
  • Completed asphalt walkway along east side of pool fence.
  • Installed roof drains.
  • Installation of radiant heat panels 90% complete.
  • Installation of exterior light poles on foundations 50% complete.
  • Installation of interior light fixtures 50% complete.
  • Decorative lighting on building exterior 75% complete.
  • Completed installation of gutter bullnose.
  • Completed installation of zero depth leisure pool walls.

4/23/14 Update
  • Bathhouse roof installation 70% complete.
  • Installed skylights in breezeway.
  • Completed drywall installation in breezeway.
  • Ceramic tile work in changing rooms 80% complete.
  • Continued painting of interior block walls.
  • Overhead plumbing ongoing.
  • Completed installation of exterior gas line.
  • Installation of radiant heat panels 75% complete.
  • Commenced installation of exterior light poles on foundations.
  • Commenced installation of interior light fixtures.
  • Completed foundations for future deep water slide.
  • Completed installation of diving well main drains.
  • Commenced installation of gutter bullnose.
  • Commenced installation of pool deck drains.
  • Commenced forming and pouring of concrete pool deck.
  • Accepted delivery of dual slide tower.

4/09/14 Update
  • Started new roof installation on the bathhouse.
  • Installed new ceiling grid system in bathhouse.
  • Continued interior metal stud work.
  • Completed curtain wall framing.
  • Completed installation of aluminum composite panels below canopies.
  • Ceramic tile work in changing rooms 40% complete.
  • Installed lockers in lifeguard room and men’s and women’s changing rooms.
  • Continued painting of interior block walls.
  • Overhead plumbing ongoing.
  • Commenced installation of exterior gas line.
  • Completed rough in of HVAC duct work.
  • Commenced installation of radiant heat panels.
  • Commenced installation of exterior underground conduit runs.
  • Commenced installation of pool circulation plumbing.
  • Installed new pool wall section near slide tower.
  • Installed deck anchors for starting blocks and backstroke stanchions.
  • Commenced installation of new underwater lights.
  • Completed excavation of zero depth leisure pool.
  • Accepted delivery of climbing wall and pool heater.

3/27/14 Update
  • Interior concrete wall construction 100% complete.
  • Continued interior metal stud work.
  • Continued painting interior block walls.
  • Cut openings in roof deck for skylights.
  • Snack bar FRP wall construction complete.
  • Installed exterior roll up doors at snack bar and storage room.
  • Overhead plumbing ongoing.
  • Completed installation of interior gas line.
  • HVAC duct work ongoing.
  • Automatic temperature controls rough in 80% complete.
  • Completed electrical rough in of walls and floors.
  • Completed main wire pull to main switchgear.
  • Installed electrical feeders to emergency panel.
  • Commenced exterior light pole foundations and conduit stubs.
  • Completed pool filtration equipment demolition.
  • Continued pool deck demolition.
  • Commenced excavation of zero depth leisure pool.
  • Removed zero depth pool wall section.
  • Completed excavation for pool main drain lines.
  • Completed pool sandblasting.
  • Commenced excavation for diving well drain boxes.
  • Excavated and set leisure pool plumbing pit on concrete footer.

3/12/14 Update
  • Concrete flooring in breezeway 100% complete.
  • Interior concrete wall construction approximately 80% complete.
  • Installed steel for exterior canopies.
  • Started interior metal stud work.
  • Started painting interior block walls.
  • Overhead plumbing ongoing.
  • HVAC duct work ongoing.
  • Commenced rough in of automatic temperature controls.
  • Commenced pool deck demolition.
  • Pool gutter demolition complete.
  • Pool shallow water section demolition complete.
  • Commenced excavation for pool main drain lines.
  • Completed set up of sandblasting equipment.
  • Excavated and set pool filtration settling tank on concrete footer.

2/26/14 Update
  • Poured concrete floor in women’s changing room, storage area and pool office
  • Concrete flooring in breezeway is approximately 80 percent complete
  • Interior concrete wall construction is approximately 60 percent complete
  • Completed exterior canopy footers and piers
  • Continuing work on overhead plumbing
  • Started work on HVAC duct work
  • Started running main electrical line from recreation center

2/13/14 Update
  • Prepared the interior sub base for concrete floor pour.
  • Poured concrete floor in snack bar and men’s changing room.
  • Completed interior concrete footers.
  • Set door frames in snack bar area.
  • Completed interior underground plumbing work.

1/30/14 Update
  • Completed removal of interior slabs
  • Completed interior grade cut to subgrade
  • Nearly finished interior concrete footers
  • Completed the deep excavation portion of the exterior storm drain work
  • Nearly completed interior underground plumbing work.

1/16/14 Update
  • Completed structural work and shoring.
  • Work on exterior storm drains continues as does electrical wiring in bathhouse.

12/16/13 Update
  • Began removal of concrete floors in bathhouse
  • Began installation of storm water piping at the bottom of the slope
  • Gas line pipe arrived on site
  • HVAC demolition is complete
  • Started demolition of exterior light poles

11/27/13 Update

  • Work on the pool project begins in earnest.
  • Completed work demolishing internal concrete walls in bath house
  • Begun demolishing bath house floors, plumbing, heating, ventilation and air conditioning, electrical.
  • Begun demolishing outdoor sidewalks
  • Demolished water slides and remove interior pool equipment

Site Plan & Exterior Elevations for the Pool Renovation project.